MU2 Progress

tmccormi wrote on Friday, June 10, 2016:

Reminder: Hardship Exception Applications are Due by July 1, 2016 for the Medicare EHR Incentive Program

bradymiller wrote on Saturday, June 11, 2016:

Hi,

Here is code by Visolve to pass the Clinical Quality Measures items. It’s already undergone several revisions and it’s likely ready to come into the codebase. I plan to bring it into the codebase soon unless anybody has issues with it. The code is here:

thanks,
-brady
OpenEMR

tmccormi wrote on Sunday, June 12, 2016:

Is this all new code or updates to the code Ensoftek contributed?

bradymiller wrote on Sunday, June 12, 2016:

Hi Tony,
It’s updating of the code contributed by Ensoftek along with completion of several unfinished pieces.
-brady
OpenEMR

bradymiller wrote on Sunday, June 12, 2016:

Hi,

Here is code by ZH Healthcare to pass the following MU2 items:
170.314(f)(1) Immunization Information
170.314(e)(2) Ambulatory setting only - clinical summary

It’s already undergone several revisions and it’s likely ready to come into the codebase. I plan to bring it into the codebase soon unless anybody has issues with it. The code is here:

thanks,
-brady
OpenEMR

tmccormi wrote on Sunday, June 12, 2016:

Just making sure they get credit as well … :slight_smile:

bradymiller wrote on Sunday, June 12, 2016:

Hi Tony,

Credit and tracking of credit is being addressed by the following:

1.All parties that have worked on an item are given credit in the item listing here:
http://www.open-emr.org/wiki/index.php/OpenEMR_Certification_Stage_II_Meaningful_Use#Certification_Criteria

2.Placed a section here that simply tallies the items by contributor:
http://www.open-emr.org/wiki/index.php/OpenEMR_Certification_Stage_II_Meaningful_Use#Acknowledgments

-brady
OpenEMR

bradymiller wrote on Tuesday, June 14, 2016:

I just committed this code into the main codebase.

-brady
OpenEMR

bradymiller wrote on Sunday, June 19, 2016:

I just committed above code into the main codebase.

-brady
OpenEMR

bradymiller wrote on Tuesday, July 26, 2016:

We are getting very close :slight_smile:
http://www.open-emr.org/wiki/index.php/OpenEMR_Certification_Stage_II_Meaningful_Use#Completion_Barometer

-brady
OpenEMR
OEMR Organization

bradymiller wrote on Monday, August 08, 2016:

Hi,

Another piece of very good news. Visolve just passed the AMC item today. Thank you Visolve!!

Thus we just have 1 more item left to pass:
http://www.open-emr.org/wiki/index.php/OpenEMR_Certification_Stage_II_Meaningful_Use#Completion_Barometer

-brady
OEMR Organization

tmccormi wrote on Friday, August 26, 2016:

How’s that last piece coming? We have to be certified and on the CMS site by Oc1 1 for anyone to be able to do MU2 this year…

cmswest wrote on Friday, August 26, 2016:

hi Tony, expect good news in 2-3 weeks.

bradymiller wrote on Saturday, August 27, 2016:

More detailed update:

  1. Usability testing (item G3) by 3 extremely generous volunteers is happening this weekend. If all goes well, then the report for this last item will be turned in next week.
  2. Turns out item a1 (CPOE) was never tested. It’s super simple and plan to get that passed next week.

So barring any more surprises, should be submitting for MU2 late next week (which can then take several weeks to process). It is going to be very close to the 10/1 deadline…

-brady
OEMR Organization

bradymiller wrote on Wednesday, August 31, 2016:

micro-update:

  1. item G3: The usability testing report has been turned in(thanks to the usability testing volunteers and visolve for working non-stop on this over the weekend).(hopefully the report will be accepted and will hear back soon on this; if so, then this item will be passed)
  2. item a1: CPOE test for cert will be done on 9/1.

I have confirmed with infogard that the above items are the only items remaining. Thus, if all stars align, we could be submitting for full MU2 cert at the the end of this week (and then there’s still a several week turn around time).

-brady
OEMR Organization

bradymiller wrote on Friday, September 02, 2016:

micro-update:

  1. item G3: Several modifications were requested by Infogard on the usability testing report. Hopefully will be turning in the revised report tomorrow.
  2. item a1: Visolve passed this item today! Thank you Visolve!

-brady
OEMR Organization

bradymiller wrote on Thursday, September 08, 2016:

micro-update:

  1. item G3: Passed. Thank you Visolve!

All items are completed and Infogard is currently verifying everything before sending application to ONC.

Check out the beautiful, all purple barometer:
http://www.open-emr.org/wiki/index.php/OpenEMR_Certification_Stage_II_Meaningful_Use#Completion_Barometer

-brady
OEMR Organization

cmswest wrote on Thursday, September 08, 2016:

Great news! Congratulations!

bradymiller wrote on Monday, September 12, 2016:

micro-update:
A “technical review” will be performed by Infogard near the end of this week, which takes several days. Once this is complete, the application then goes to ONC and takes 7 business days. So, if all goes well, then plan to release 5.0.0 with complete MU2 prior to 9/30/16. Keep fingers crossed :slight_smile:

-brady
OEMR Organization

tmccormi wrote on Wednesday, September 14, 2016: